Power Demand and Local Impact
The announcement comes amid growing local concern over the energy consumption of data centres. In August, Ottawa city council passed a motion directing staff to develop a framework for assessing data centre proposals, looking at environmental standards and community benefits.
Bryce Conrad, CEO of Hydro Ottawa, told council in June that the utility had received 34 requests in the past two years for "large load customers." These requests would require nearly 90 per cent of the average amount of power used by the City of Ottawa in 2025. Conrad noted that data centres accounted for 653 megawatts of the 1,075 megawatts requested to Hydro Ottawa.
"It’s no secret that there’s a lot of tension these days around data centres, AI technologies, and their tremendous appetite for power," Conrad said. He added that Hydro Ottawa is working to build capacity, stating, "We’re probably being asked to build in the next two or three years, that which has taken us about 110 years to build."