Data centre restrictions
The bill restricts data centre projects of 10 megawatts (MW) or larger from being built within 600 metres of the nearest home or on “high-quality” farmland. Centres of that size would also be prohibited on irrigated land, which the province reports would protect about 14 million acres of Class 1 and 2 agricultural land.
The Alberta Utilities Commission (AUC) would become the regulator of all centres 10 MW or larger, ensuring projects are held to the same noise and light standards as power plants. The bill would also support regulations defining efficiency standards for water use.
Projects with already approved permits will not be subject to the new policies. The province reports that 70 data centres are working with its concierge program and that 30 per cent of those could be impacted by the new policies.
Technology Minister Nate Glubish said the changes respond to Albertans’ concerns and cited the rejected 1.4-gigawatt (GW) facility proposal in Olds. “This will give communities like Olds that confidence that this can never happen in their backyard, and they don’t have to wait for months and months and months for a regulatory process to unfold,” Glubish said.