Rapid Deployment vs. Grid Delays
The primary driver for using aeroderivative turbines—which are rebuilt from retired aircraft engines to run on natural gas—is the speed of deployment. Rystad Energy analyst Audun Martinsen told The New York Times that "they can have a data center running in 24 months" using jet-powered units.
In contrast, the International Energy Agency reports that connecting 100 megawatts to the grid in Northern Virginia takes approximately seven years. Furthermore, an executive at Mitsubishi Power told Bloomberg that most new power capacity is not expected to come online until 2031.